Palm oil · 2025

Decanter panel broken? Build a new one

The decanter's original control panel failed. I designed and built a new one from scratch that can be maintained locally.

Client
PT Prima Tetap Jaya
Year
2025
Location
North Sumatra
My role
Design
Delivered through
Firmansyah.co, as subcontractor to PT Prima Tetap Jaya

Layers worked on

  1. 01Field
  2. 02Logic
  3. 03Telemetry
  4. 04Screen

What we did

  1. 01Schneider Electric PLC and HMI replacing the original panel.
  2. 02Decanter motors driven through inverters.
  3. 03Clean-in-place (CIP) sequence runs automatically from the new panel.
LocationNorth Sumatra

The result

The decanter is back in service on a locally built, maintainable panel with automatic CIP.