Low-pressure boiler control, fully replaced

The low-pressure boiler controls at Lubuk Gaung were worn out. We replaced them with Siemens PLCs and logic that keeps the drum safe.

Client
Sinarmas · PT Ivo Mas Tunggal Lubuk Gaung
Year
2025
Location
Dumai, Riau
My role
Lead engineer
Delivered through
Xtend Integrasi Indonesia, as subcontractor to Mechmar

Layers worked on

  1. 01Field
  2. 02Logic
  3. 03Telemetry
  4. 04Screen

What we did

  1. 01New Siemens TIA Portal PLC program replacing the old controls.
  2. 02Three-element feedwater control (drum level, steam flow, feedwater flow) to prevent carryover and tube burnout.
  3. 03Inverter-driven forced and induced draft fan modulation with burner safety interlocks.
  4. 04JSA, method statements and termination diagrams.
LocationDumai, Riau

The result

The boiler now runs on three-element feedwater control and new burner interlocks. Steam supply to the refinery is secured.