14 weeks after a flash flood, back in full production

The December 2025 flash flood submerged PT Intibumi's aluminium plant. Its control panels and programs had to be rebuilt.

Client
PT Intibumi Alumindotama Industry
Year
2026
Location
North Sumatra
My role
Supervision
Delivered through
Xtend Integrasi Indonesia

Layers worked on

  1. 01Field
  2. 02Logic
  3. 03Telemetry
  4. 04Screen

What we did

  1. 01Panels and programs for the 7-ton and 15-ton annealing ovens rebuilt in Siemens TIA Portal V19, three-zone temperature control with PID_Temp.
  2. 02High-speed cut-to-length line on Nidec Unidrive M701 drives redesigned.
  3. 03Coil slitting line and eight punch presses brought back to life.
LocationNorth Sumatra

The result

Full production restored within 14 weeks with zero safety incidents. Oven temperature held within ±1.0 °C and cut-to-length accuracy within ±0.5 mm.